This project will replace the Middlebury pump station, eliminate the Yacavona pump station and install a new sanitary sewer along Middlebury Rd.
The pump stations were built in the 1960’s and are deteriorating quickly. Combining the two pump stations into one will reduce operational and life cycle costs.
As part of the project, a section of Middlebury Rd. is closed for the duration of the project.
Cost is $2 million, covered in total through a loan from the Ohio EPA’s Department of Environmental and Financial Assistance (DEFA).
Work began in October 2021 and is expected to be completed in Summer 2022.